Throughout my career spanning 25 years, I have demonstrated a wealth of relevant skills and expertise in carrying out the assigned roles in a professional manner and proved to be a dedicated, hardworking and reliable team member. I have successfully assumed various positions with owners, consultants and major contractors in my career helping me enhance my skill sets in the field of project management, engineering management, bid engineering and project controls.
I have a thorough understanding of the processes and activities pertaining to the complete life cycle of the project, project definition to handover. I am highly conversant with activities pertaining to project development, Feasibility study, concept optimization, FEED, preparation of Scope of work & ITT package, Tendering, engineering coordination, project control, progress monitoring, EPC bid engineering and cost estimation with through exposure to Petrochemicals and oil and gas upstream industries.
-
Roles / Responsibilities
- Develop Project Initiation Note (PIN) Package based on the draft Statement of Requirement from PIN originators.
- Facilitate nomination of PIN Package Team Leader (PPTL) and PIN Package Team (PPT) members.
- Liaise with PIN originator to clarify the queries raised by the PIN Package Team on the Statement of Requirement.
- Finalize the Statement of Requirement (SOR) in coordination with the PIN Package Team and PIN originator.
- Obtain Stage gate estimate and Stage gate schedule from project services department
- Compile the final PIN Package including all deliverable required for Stage Gate # 1 approval.
PIN Packages Developed
Project Brief Survey, Design, Installation and Hooking up of New Khuff gas wells and Arab D Gascap Recycling Wells to Respective Production/ injection Facility at Dukhan. Systems / Equipment Flow Line Hookup to well
WHTP
Wellhead SCADA
Choke Valves
Flow Line
InstrumentationProject Brief Replacement of 9 nos. of Not Fit for purpose pipelines , along with its associated facilities and modifications enhancement for safe operation and maintenance of Station S. Systems / Equipment Pipelines
Pig Launcher
Pig Receivers
Pressure Control Valves
ESDVs
Relief Valves
Condensate Drum PumpProject Brief Early production to allow stabilization of the production decline of the Arab D reservoir to around 40,000 Bopd. Systems / Equipment Four (4) nos. Well Head Platforms
One (1) no. Manifold Platform
Associated inter-field flow lines, gas-lift lines and Umbilicals
New Gas lift and LP Production pipelines & Umbilicals
One (1) no. 14” export pipeline -
Roles / Responsibilities
- Prepare and finalize Scope of Work and its attachments for conducting the study.
- Carryout Technical and commercial bid evaluation of the offers received from bidders and issue award recommendation.
- Manage contractor’s study activities including options screening, options selection, feasibility and concept optimization.
- Manage the HSSE aspects of the design (HAZID, WHAT IFs, HAZOPS, ENVID, PRA, Project F& S philosophy) to assure compliance with Company’s established HSE policies and procedures.
- Identify, evaluate and manage issues / events that may constitute an increase or decrease in scope, safety, project quality, cost, or schedule.
- Conduct presentation to study focal points and management to facilitate approval of selected option and the concept optimization study to proceed further to FEED.
- Collate and finalize the FEED Scope of Services and its attachments.
- Responsible to Upload the feasibility study in SAP and obtain gate # 2 approval from Management.
Feasibility & Concept Optimization Studies
Project Brief To assess the fire protection system at Khatiyah North Degassing Station and suggest suitable modifications.
To conduct a root cause analysis of the GRE piping failures at all degassing stations to recommend remedial measures for long term integrity of the GRE piping.Systems / Equipment Fire water storage tank
Deluge System
Hydrants and Monitors
Fire Water Ring Main
Surge Analysis Reports
Stress Analysis Reports
RCA ReportsProject Brief To install a integrated gas supply network to ensure uninterrupted supply of lean gas to Mesaieed consumers and Facility D.
To tidy the existing individual pipelines to the consumers.
To install custody flow metering for accurate measurement of gas supplied to the consumers.Systems / Equipment Extension of Existing Block Valve Station
Lean Gas Filters
HP to MP Pressure Let Down Valve
HP to LP Pressure Let Down Valve
HIPPS
Pipeline Headers
Custody Flow Meters
ESDVs
MOVs
Four (4) nos. metering StationsProject Brief To assess the adequacy of the existing process and utility system at degassing stations and power water injection stations and recommend modifications to support implementation of the the Enhanced Water Flooding in order to meet the DFIS production forecast.
The study included assessment of seven (7) nos. degassing stations and nine (9) nos. powered water injection stations.Systems / Equipment Oil Producer Wells
PW Injector Wells
Oil flow lines, Gaslift lines and PWI spur lines
Oil and Gaslift manifolds
Three Phase Production Separators
Hydrocyclones
Secondary PWT
Degassing Vessels
PW Transfer Pumps
PW Transfer Pipelines
Associated Gas Compressor
Oil Transfer / Production Lift Pumps
Crude Oil Tanks
Main Oil Line Pump
TEG Dehydration
RAG Dehydration
PWI Booster Pumps
HP and LP Flare
Feeder Pipelines
Hot Oil UnitProject Brief To assess the adequacy of process and utility system at the existing gas stripping plant and gas recycling plant and recommend modifications to meet 30 years production forecast as part of the infill drilling and enhanced water flooding (EWF) upgrade.
The study included assessment of Fahahil Stripping Plant (FSP) and Gas Recycling (Arab D) Plants for 10 years until 2028.Systems / Equipment Stripper Column
Stabilizer Column
HP Demethanizer
LP Demethanizer
Stripper Reboiler
Stabilizer Reboiler
I Stage Stripper Preheater
II Stage Stripper Preheater
Stabilizer Overhead Pump
NGL Pipeline Pump
Condensate Pipeline Pump -
Roles / Responsibilities
- Lead the task force of discipline engineers / designers and make certain that the team is aware of all the technical elements of the project and nature of work.
- Ensure the scope of the project and inter discipline activities are fully understood and covered by all discipline engineers to ensure total scope coverage without missing areas or duplication.
- Manage effective interdisciplinary coordination to ensure integrated and complete designs that meet project and contractual requirements.
- Provide the necessary technical decisions in case of unresolved conflicts among disciplines and act as focal point between non technical disciplines such as procurement, contracting and construction and the engineering team.
- Act as a representative of company towards client in all technical matters and manage technical issues / changes presented to the client and ensure that they are resolved and ensure incorporation of the changes.
- Manage the HSSE studies of the FEED (HAZID, HAZOP, Project F& S philosophy) to assure compliance with Company’s established HSE policies and procedures.
- Identify, evaluate and manage issues / events that may constitute an increase or decrease in scope, safety, project quality, cost, or schedule.
- Collate and finalize the EPIC SOW and its attachments.
FEED Projects
Project Brief To upgrade the internals of the seven (7) nos. of existing 3 Phase production separators at Khatiyah North, Khaityah South and Khatiyah Main to improve the Water in Oil (WIO) outlet specification.
To provide piping early tie-ins to facilitate implementation of the modifications pertaining to Dukhan Production Facilities Upgrade upgrade without additional shutdown.Systems / Equipment 3 Phase Production Separator
Process Tie-ins
Utility Tie-insProject Brief To upgrade the internals of the two (2) nos. of existing 3 Phase production separators at Jaleha Degassing Station to improve the Water in Oil (WIO) outlet specification.
Replacement of two (2) nos. hydrocyclones with new hydrocylcones having high efficiency liners.
To install new internals at Diyab slug catcher and Wet Lift Gas KO Drum to improve their performance.
To provide piping early tie-ins to facilitate implementation of the modifications without additional shutdown.Systems / Equipment 3 Phase Production Separator
Hydrocyclones
Diyab Slug Catcher
Wet Liftgas KO Drum
Process Tie-ins
Utility Tie-insProject Brief To extend the existing block valve station to install facilities for letting down HP to MP and HP to LP.
To install an integrated lean gas supply network to ensure un-interrupted supply to Mesaieed consumers.
To install fiscal metering stations for accurate metering of the gas being supplied to consumers.Systems / Equipment Extension of Existing Block Valve Station
Lean Gas Filters
HP to MP Pressure Let Down Valve
HP to LP Pressure Let Down Valve
HIPPS
Pipeline Headers
Custody Flow Meters
ESDVs
MOVs
Four (4) nos. Metering Stations
Gas Chormotographs
Tie-in to Consumer FacilitiesProject Brief Installation of seven (7) nos. of Sensor Tower Platforms at offshore for surveillance of offshore facilities.
Installation of Forward Mounting Base including Accommodation Platform bridge connected with Utilities Platform.Systems / Equipment Sensor Tower Platform
Diesel System
Accommodation Platform
Utilities Platform
Heli Fuel System
Chilled Water System
Electrical Facilities
Subsea Power and FO Cables -
Roles / Responsibilities
- Handle assigned projects (Design Change Requests) ranging from minor modifications through to new installation / construction. Monetary values typically range from $100K to $20M.
- Manage the engineering activities pertaining to plant modifications and liaise regularly with Operations and safety Departments to ensure the engineering design is acceptable to such user departments.
- To carry out design and detail engineering for the proposed plant modifications and obtain approval from Design Change Subcommittee (DCS) prior to implementation
- Prepare Scope of Work for the construction contract
- Perform Technical and Commercial Bid Evaluation and issue contract award recommendation
- Supervise and direct construction contractor / maintenance team during implementation of the plant modification.
- Responsible for site construction HSE activities including Permit To Work(PTW).
Site Projects
Project Brief Execution of various projects initiated to modify the existing plant facilities and /or install new facilities to augment the plant. Systems / Equipment PE Pilot Plant
PVC Pilot Plant
SABCAT Plant
PP Catalyst Plant
LAO Pilot Plant
Technical Support Laboratories
R&D LabsProject Brief Installation of a bench scale PDU along with the utilities required. PDU unit was built to convert Ethane to Acetic Acid at SABIC Industrial Complex at Riyadh. Systems / Equipment PDU Reactor
Air Cooled Water Chiller
Ethane Cylinder Banks
Steam Drum
Separation Test Rig (STR)
Vapor Liquid Equilibrium (VLE)Project Brief Procurement and Installation of Additional Ethylene purification skid and pump. Systems / Equipment Ethylene Purification Skid
Ethylene Pump
Fire Water System
Fire Protection SystemProject Brief Installation of various PE, PP, PVC bench scale reactors for the Research and Development. Systems / Equipment Bench Scale Reactor Skids
High Pressure Cylinder Banks
Fume Hoods
Pressure Regulators
Process TubingProject Brief Install 90TR process chilled water system, chilled water supply and return piping network. Systems / Equipment Air Cooled Water Chiller
Chilled Water Tank
Chilled Water Supply Header
Chilled Water Return Header
Electrical WorksProject Brief Installation of Fire protection system at PP Catalyst warehouse, Hydrocarbon storage tanks and offices. Systems / Equipment Fire water piping network
Deluge System
Dry and Wet Pipe Sprinklers
Fire Water Ring Main Tie-ins
Hydrocarbon storage tanks
PP Catalyst Warehouse -
Roles / Responsibilities
- Lead the task force of discipline engineers / designers assigned for EPC proposals and make certain that the team is aware of all the technical elements of the project and nature of work.
- Ensure the scope of the tender and inter discipline activities are fully understood and covered by all discipline engineers to ensure total scope coverage without missing areas or duplication.
- Manage effective interdisciplinary coordination to ensure effective bid engineering that meet tender and client requirements.
- Act as a representative of company towards client in all technical matters and manage technical issues / changes presented to the client and ensure that they are resolved and ensure incorporation of the changes.
- Responsible for producing bid engineering deliverables including engineering man hours, Bulks MTO, procurement RFQs, Construction BOQ, etc.
- Manage post tender clarifications and participate in techno commercial meetings with client and close out all technical issues for EPC proposals.
- Conduct brainstorming ROKM sessions to identity and prepare list of Risks and opportunities along with quantitative assessment to finalize the cost contingencies.
EPC Proposals
Company Qatar Petroleum, Doha Project Brief EPIC PART 1 - To upgrade the existing Sulphur Recovery Unit (SRU) facilities (310 MTPD) at NGL-3 Plant in Mesaieed to achieve 99.5 % sulphur revocery to comply with state environmental regulations.
EPIC PART 2 - To implement a new Acid Gas Recovery Unit (AGRU) of 450 MMSCFD capacity at Arab D facilities in Dukhan.Systems / Equipment for SRU - EPIC Part 1 Acid Gas Enrichment Unit
Existing SRU Facilities Upgrade
Tail Gas Treating Unit (TGTU)
Tail Gas Incinerator
Sea Water Cooling System including Jetty
Boiler Feed Water and Steam System
Electrical Power System
Control and Safety SytemsSystems / Equipment for AGRU - EPIC Part 2 Amine Package
TEG Dehydration Unit
Acid Gas Compression Facilities
Sour Gas Pipeline
Sweet Gas Pipeline
Hot Oil System
Effluent Water Treatment
Electrical Power System
Control and Safety SytemsCompany ADCO, Abu Dhabi Project Brief To develop the Thamama-G (Th-G) and Habshan 2 (H-2) reservoirs to achieve sustainable production rates of 60,000 BOPD and 20,000 BOPD, respectively.
To export a peak of 465 MBOPD of stock tank crude oil from the Bab Central Degassing Station (BCDS).
The Project included four (4) nos. Remote Degassing Stations (RDS) and Modifications to existing Central Degassing Station (CDS) at BABSystems / Equipment for RDS Inlet Manifold
Production and Test Headers
Blowdown System
Flare KO Drum and Pump
Instrument Air System
Chemical Injection System
Raw Water System
Pig Launchers and Transfer Lines
Production Separator Upgrade
Produced Water Disposal System
Water Injection Clusters
Wash Water System
Effluent Water System
HP Flare Headers
Nitrogen Generation System
Closed Drain SystemCompany ZADCO, Abu Dhabi Project Brief To sustain oil production to 25,000 Stbd at the offshore Satah Field Facilities through gas injection. Systems / Equipment Modification to Six (6) Wellhead Platforms
Test Separators
Pig Launchers
Modification to Production Manifold Platform
Pig Receivers
Flare KO Drum
Flare Boom
Propane Package Skid
Chemical Injection Skids
Diesel Storage and DG Set
Pipeline Risers
J Tubes
Pig Receiver
Modifications at Onshore Zirku Island
Glycol Dehydration Unit
Off Gas Compressor
Gas Injection CompressorCompany Petronas Carigali Pakistan Limited (PCPL), Pakistan Project Brief To develop the Mehar field by installing well head facilities, gas gathering facilities and Gas processing facility to process 55 MMSCFD gas production and 6600 BPD of condensate. Systems / Equipment Wellhead Facilities
Flow Lines
Gathering Manifold
Trunk Lines
GPF Inlet Manifold
Inlet Separator
Booster Compressor
Gas Sweetening Unit
Gas Dehydration Unit
Dew Point Control Unit
LPG Extraction Unit
Export Gas Compressor
Flash Gas Compressor
Condensate Stabilization Unit
PW Treatment Package
LPG Bullets
Condensate Storage TankCompany Saudi Aramco, Saudi Arabia Project Brief To upgrade crude gathering and power supply facilities at nine (9) nos. existing platforms - Phase I Safaniya Field.
To prepare the plaform for installation of Electrical Submersible Pump (ESP) and reconnect the piping and instrumentation.
To existing Tie-in platforms and GOSP & Install flow lines and submarine cables.Systems / Equipment Hookup works for WHP and Tie-in Platforms
VSD and Transformer for Electrical Submersible Pump (ESP)
Distribution Transformer
Power Distribution Panel
MOVs
ESD and RTU Cabinets
Corrosion Inhibitor Skid
Slops DrumCompany ZADCO, Abu Dhabi Project Brief To expand the gas handling capacity of the Upper Zakum Treatment Platn (UZGTP) at Zakum Central Complex by installation of 2 nos. LP Compressor modules along with up gradation of existing primary section of Gas Treatment Plant to achieve oil production target of 750 STMBOPD Systems / Equipment LP Gas Compressor Module
Propane Refrigeration Unit
TEG Regenerator Package
Pressure Vessels
Centrifugal Pumps
Shell and Tube Heat Exchangers
Air Compressors
Air Dryers
EOT Crane